Merge Shells

This is generally the first step to producing a manageable set of phases to work with. The Target column has been specified as an attribute indicating total tonnes. The plus or minus buttons allow you to add or subtract phases. In this case, the first phase is set to 100,000, second phase is set to 250,000 etc. Note, a counter is also provided at the base of the dialogue showing the remaining tonnage. In this case, three phases have been defined and the remaining tonnage is automatically pushed into phase three.

The results will displayed in the Viewer tab and the resultant tonnages can be examined by clicking on the Report tab. You can also define the Calculated Stage legend as well in the Viewer Manager. Phase will accumulate the tonnes to the nearest shell. Note, this option will not cut across shells, but will only accumulate shells.

Mining Rules

The Mining Rules function takes each block and attempts to place it in a template of given dimension with blocks that have the same stage. For example, consider a 3 x 3 template. Each block lies in one of nine such templates with eight other blocks (with some overlap between templates). If a block cannot be placed in such a template, the stage values of some of the blocks in one of the templates must be changed so that the block does lie in an admissible template. The tolerance argument for this function represents how many blocks in a template must share the same stage for the block to not need its stage changed. For example, a 3 x 3 template with tolerance of two indicates that 9 - 2 = 7 blocks in the template must share the same stage as the block in question for the template to be considered valid.

If propagation behaviour is enforced, the changes will be applied upwards at the slope angle defined in the initial stages of setup.

Advanced

To produce results with more finesse, some of the advanced tools may be more appropriate. These include:

Drop Cut and Small Walls

When mining out a phase, the bottom of a phase can have holes or drop cuts which are impractically small to mine. These functions attempt to smooth out the stages created by eliminating small walls and drop cuts of the input size.

Add/Remove/Combine Stage

Add a stage

This option allows you to initialise an empty stage. This stage will be initially invisible to the user. Automatically, the existing stages will be incremented by one.

Remove a stage

This option allows you to remove a stage from the model.

Combine a stage

This option allows you to combine two stage into a single phase as shown below:

Split Stage

Contiguous

This option allows you to split shells which are separate, but have the same phase ID into separate phases.

Line

This option allows you to split shells which are not separate, into separate phases.

Block Edit

Block editing provides a mechanism to modify and create stages in a model based on block positioning and geometry.

To edit a set of blocks, complete the following steps:

  1. Go to the Advanced tab and select the Block Edit option to open the panel in the Phase Design window.

  2. Block editing can be applied in three different ways: Above, Below or only on the selected blocks. Select the propagation behaviour you would like to apply.

  3. Select a target stage.

  4. Select the blocks to edit.

  5. Click OK.

  6. Changes will be made based on the information provided.

It is important to note that phase creates stages to be mined in order i.e. if there were two stages - 1 and 2, 1 would be mined before 2. How far the changes propagate depends on the target stage chosen. In the image below, where the Below option was selected, because the target stage was set to a value greater than the existing stages, the new stage has propagated to the bottom of the model.

This is a sensible outcome, as the target stage is to be mined after the existing stages, making this configuration possible. If the target stage was set to a value lower than the existing stages, the new stage would only have included the selected blocks. The configuration above would not be possible if the target stage was set to a lower value, as convention dictates that it would need to be mined first. The opposite will occur if the Above option was selected.