Targets

The Calendar > Targets sub-tab is used to define parameters per period in the production cycle. The Calendar sub-tab has three separate sections: Calendar toolbar, Summary, Targets and the Resource specific section.

Calendar toolbar

How to generate multiple periods

  1. To generate multiple periods at once, click the lightning bolt icon in the Calendar toolbar.
  2. This will open up a new panel. Provide the said information and click OK.

How to add/ delete diggers

  1. Click the digger icon in the Calendar toolbar.
  2. This will bring up a new panel.
  3. To add diggers, click the drop down menu next to the green plus icon. Adjust the number of diggers that are required by clicking the plus or minus buttons and then click Add.
  4. To delete diggers, select a digger from the list and then click the red minus icon.

How to add a period

  1. Click the drop down arrow next to the green plus icon in the Calendar toolbar. Adjust the number of diggers that are required by clicking the plus or minus buttons and then click Add. The periods will be add to the end of the list. To insert periods before a selected period, click here.

How to delete a period

  1. Select a period.
  2. Click the red minus sign in the Calendar toolbar.

How to insert a period before selected period

  1. Select a period in the Calendar.
  2. Click the insert icon in the Calendar toolbar.

How to split a period

In reserve setups, it isn't necessary for all periods to be the same length or have a time frame of a month. It is also possible to have periods in reserve that are fortnightly, monthly, quarterly or yearly. But be mindful that this will have an effect on the NPV.

To split a period:

  1. Select a period in the Calendar.
  2. Click the Split Into dropdown menu in the Calendar toolbar.
  3. From the drop down list, select a time unit to split the period into.

Summary

In the Summary section, you can define the number of days per period that the site is actively mined.

Targets

In the Targets section, when to end the period, otherwise known as the end of period target.

There are four types of end of period targets to select: Total Tonnes, Ore Tonnes, Haulage Hours and Volume.

  • For a Total Tonnes or Volume end of period target, a target value needs to be provided.
  • The Ore Tonnes end of period target is equal to the mill capacity set for the period.
  • The Haulage Hours end of period target is equal to the Total Haulage Hours calculated by the software.

Resource-specific

The following resources have their own section in the Calendar sub-tab: Digger, Mill and Stockpile.

Digger

For each digger added in the Diggers sub-tab, the availability in terms of hours and production range, is calculated per period.

Mill

The mill's capacity and ore definition are provided on a per period basis. If ore tonnes are set as the end of period target, the software will end the period when the mill's capacity has been reached. The ore definition describes the type of material that can be processed by the mill. An example of an ore definition would be the following:

block.oretonnes/block.totaltonnes > 0.75

This means that the mill can only process material with a percentage of ore greater than 75%.

Stockpile

Three fields need to be defined periodically for a stockpile: ore definition, manual reclaim and a reclaim mill. The ore definition is used to restrict material going to a stockpile. This definition needs to be mutually exclusive to the definition provided to the mill. The manual reclaim field is to specify the maximum amount of material that can be sent from the stockpile to the associated mill. The associated mill is set in the reclaim mill field.