Net Present Value
The NPV objective is used to perform value calculations during a schedule optimisation, which generates higher values based on costs and revenue.
The NPV tab is used to assign more complex economic costs to the setup. These include:
- Discount rate — The value lost per period.
- Mining cost — The cost to physically remove material.
- Processing cost — The cost associated with mill usage.
- Rehabilitation cost — The cost per ton applied to transport material to a waste utility.
- Rehandle cost — The cost per ton applied to material taken from a stockpile.
- Reclaim — The cost per ton to transport material from a stockpile to a mill.
- Recovery— The percentage for recovering material from a stockpile.
The Calendar > NPV tab is used to assign basic NPV costs and value on a per period basis.