Stage Availability

The Stage Availability constraint allows you to flag the availability of pit stages per period.

To create a stage availability constraint:

  1. From the setup configuration tabs, select 7. Constraints.

  2. Use the slider at the bottom of the viewer to navigate to Stage Availability.

  3. Click to add the constraint to your schedule.

  4. Under Applied Constraints, click on Stage Availability to open the constraint settings.

    In the settings table, all of the stages are initially set to available which is indicated by the green cells.

  5. Double-click the cell of the stage and period you wish to make unavailable. The cell will turn red when it is disabled. Similarly, you can make a stage available again by double-clicking the cell.