Bench Release
The Staging > Bench Release tab allows you to specify the order you wish to mine the stages. There are four fields:
- Stage: The predecessor stage that needs to be mined first.
- Dependent stage: The successor stage linked to the predecessor stage.
- Benches: The number of benches that are required to be mined in the predecessor stage before moving on to the successor stage.
- Mine Completely: When selected, indicates that the predecessor stage must be completely mined before moving on to the successor stage.