Bench Accumulation
Source file: origin-reserve-setups-constraints-bench-accumulation.htm
Use the Bench Accumulation constraint to set the maximum amount that can be mined per bench per period. Benches are grouped in terms of stage.
The Item drop-down menu allows you to specify the item to set the accumulation constraint against.
You can apply settings manually for each stage in each period, or by copying the entered setting to the next period using the button. To copy the setting to all subsequent periods double-click the button. Alternatively, copy a cell's setting using Ctrl + C, then paste into selected cells with Ctrl + V.