Use the Pit Region Availability constraint to make specific regions of a solid available to mine per period.
To use this constraint, you need to first populate the table with regions by selecting an attribute from the imported pit. Examples of attributes from the drop-down menu that you could set to a Region include bench or stage.
The stages that are available for mining in a given period are marked in green, whereas these that cannot be mined in a given period are marked in red. To change the region mining availability, double-click on the corresponding cell and select the required status.
You can apply settings manually for each stage in each period, or by copying the entered setting to the next period using the button. To copy the setting to all subsequent periods double-click the button. Alternatively, copy a cell's setting using Ctrl + C, then paste into selected cells with Ctrl + V.