2. Configure the Setup
Source file: 2-origin-solids-setup-configure.htm
Once an Origin Solids setup is created, it needs to be configured so that it contains the necessary information for schedule generation.
Origin Solids setup configuration is divided into a number of tabs. Each tab represents an aspect of the setup the software requires to schedule the mine. The following is a list of tabs that need to be configured for an Origin Solids setup to be ready for server submission:
- Process Setup: Used to add process flow components to a setup.
- Objectives: Used to define specific outcomes the schedule aims to achieve.
- Calendar: Used to define targets per period.
- Mining: Used define a miscellaneous set of setup constraints.
- Constraints: Used to define a set of setup constraints per period.
- Other: Used to define constraints surrounding schedule generation.
- Viewer: Provides a 3D display of models within the setup.