Bench Accumulation
Source file: origin-reserve-setups-constraints-bench-accumulation.htm
Use the Bench Accumulation constraint to set the maximum amount that can be mined per bench per period. Benches are grouped in terms of stage.
The Item drop-down menu allows you to specify the item to set the accumulation constraint against.
-
Click the
button once to copy the properties of the current period to the next period.
-
Double-click the
button to copy the properties of the current period to the subsequent periods until the end of the schedule.
-
Alternatively, copy a cell's setting using Ctrl+C , then paste it into selected cells with Ctrl+V.