Bench Accumulation

Source file: origin-reserve-setups-constraints-bench-accumulation.htm

Use the Bench Accumulation constraint to set the maximum amount that can be mined per bench per period. Benches are grouped in terms of stage.

The Item drop-down menu allows you to specify the item to set the accumulation constraint against.

  • Click the button once to copy the properties of the current period to the next period.

  • Double-click the button to copy the properties of the current period to the subsequent periods until the end of the schedule.

  • Alternatively, copy a cell's setting using Ctrl+C , then paste it into selected cells with Ctrl+V.