Pit Accumulation

Source file: origin-reserve-setups-constraints-model-accumulation.htm

Use the Pit Accumulation constraint to define the maximum volume or amount of tonnes that can be mined per pit per period.

The Item drop-down menu allows you to specify the item to set the accumulation constraint against.

  • Click the button once to copy the properties of the current period to the next period.

  • Double-click the button to copy the properties of the current period to the subsequent periods until the end of the schedule.

  • Alternatively, copy a cell's setting using Ctrl+C , then paste it into selected cells with Ctrl+V.