Pit Region Availability
Source file: origin-reserve-setups-constraints-pit-region-availability.htm
Use the Pit Region Availability constraint to make specific regions of a solid available to mine per period.
To use this constraint, you need to first populate the table with regions by selecting an attribute from the imported pit. Examples of attributes from the drop-down menu that you could set to a Region include bench or stage.
The stages that are available for mining in a given period are marked in green, whereas these that cannot be mined in a given period are marked in red. To change the region mining availability, double-click on the corresponding cell and select the required status.
-
Click the
button once to copy the properties of the current period to the next period.
-
Double-click the
button to copy the properties of the current period to the subsequent periods until the end of the schedule.
-
Alternatively, copy a cell's setting using Ctrl+C , then paste it into selected cells with Ctrl+V.