Process Accumulation

Source file: origin-reserve-setups-constraints-process-accumulation.htm

Use the Process Accumulation constraint to restrict the maximum amount of material a mill can process per period.

The Item drop-down menu allows you to specify the item to set the accumulation constraint against.

The cells marked in green in the table indicate that the target has been enabled for the corresponding period. Double-click on the cell to disable the target for the required period. The cell will change its status to Unavailable and will turn red. The value assigned below for the corresponding mill will be dimmed.

  • Click the button once to copy the properties of the current period to the next period.

  • Double-click the button to copy the properties of the current period to the subsequent periods until the end of the schedule.

  • Alternatively, copy a cell's setting using Ctrl+C , then paste it into selected cells with Ctrl+V.