Stage Accumulation
Source file: strategy-setups-constraints-stage-accumulation.htm
Use the Stage Accumulation constraint to specify a maximum constraint for any item in the model, on a stage by period basis.
You can use this constraint to limit items like the following:
-
Ore tonnes
-
Total tonnes
-
Drilling hours
-
Acid consumption
-
Contaminant levels
Note: The Stage Accumulation constraint is a hard constraint.
To configure the stage accumulation, select an attribute from the Item drop-down and then specify the maximum amount of material that can be mined from a stage in each period.
-
Click the
button once to copy the properties of the current period to the next period.
-
Double-click the
button to copy the properties of the current period to the subsequent periods until the end of the schedule.
-
Alternatively, copy a cell's setting using Ctrl+C , then paste it into selected cells with Ctrl+V.