New

Add an Activity


Click New or press Shift+A to add a new activity.

Use the Activity Information panel to add or modify activity information. This panel includes general activity information as well as information about precedences, scheduling constraints, and resource allocation and rates.

Note:   You must set up attributes prior to creating activities.  See the Attributes topic for more information.

Tutorials

Click to read the Creating Activities and Viewing and Interacting with Activities tutorials.


Instructions

On the Home tab, in the Activities group, click New to create a new activity, or Properties to view the properties of an existing activity.

This panel has two tabs: the General tab and the Resources tab.

General Tab

General

This section includes general information about the activity and its progress.

Name

Enter the name of the activity.

Is summary

Select this check box if the activity is a summary.

Start

Enter or select a start date for the activity.

End

Enter or select an end date for the activity.

Work

Enter the number of days the activity is expected to take to complete.

Percent Completed

Enter the percentage of work that has been completed for the activity.

Priority

Enter a number to indicate the priority of the activity.

Predecessors

This section displays information about any predecessors that are linked to the activity. For more information about precedences, see Precedence Information.

Predecessor

Displays the predecessor's name.

Type

Select whether the activity should be linked to the start or finish of the predecessor.  You may select Start to Start, Finish to Finish, Start to Finish, or Finish to Start.

Lag

Enter the number of days that must separate the activity from the predecessor.

Successors

This section displays information about any successors that are linked to the activity. For more information about precedences, see Precedence Information.

Successor

Displays the successor's name.

Type

Select whether the activity should be linked to the start or finish of the successor.  You may select Start to Start, Finish to Finish, Start to Finish, or Finish to Start.

Lag

Enter the number of days that must separate the activity from the successor.

Scheduling Constraint

This section specifies any scheduling or time constraints for the activity.

Constraint type

Select a scheduling constraint type to indicate how early or late the activity can start or finish.  You can specify whether the activity must start or finish on/before/after a specific date, or you can specify that the activity should begin as soon or as late as possible.

Constraint date

Select a date to correspond with the Constraint type you selected. This box is disabled if you select As Soon As Possible or As Late As Possible as the Constraint type.

Click the Resources tab to continue.


Resources Tab

Resource Allocation

This section includes any resources that are allocated to the activity. For more information about resource settings and allocation, see Resources and Allocate Resources.

Resource

Select the name of the resource from the list. For more information about adding or modifying resources, see Resource Settings.

Rate

Displays the rate of the selected resource.

Rate

This section indicates the rate of the resources that are allocated to the activity.

Activity rate

Enter the activity rate.

Combined resource rate

Displays the sum of the rates from all resources that are allocated to the activity.

Resource manual rate

Enter the manual rate of the resources.

Partial parallel rate

Enter the rate of the resources when applied across multiple activities that are occurring in parallel.

Partial series rate

Enter the rate of the resources when applied across multiple activities that are occurring in series.

Source

Select a source from the list to display its current rate.

Current rate

Displays the current rate of the source selected from the Source list.