Groups
Use Groups to add, modify, and remove attribute groups.
Instructions
On the View tab, in the Group group, click Groups to display the Group Setup pane.
|
|
Add a new item. (Insert) |
|
|
Copy (CTRL + C) |
|
|
Remove (Del) |
|
|
Set Current |
|
|
Reset Current |
General
Name
Enter a name for the group.
Description
Enter a brief description of the group.
Details
Attribute
Select an attribute from the list. For more information about managing and modifying attributes, see Attributes.
From
Enter a value for the beginning of the group selection.
Length
Enter the length of the group.
Sort Order
Select whether to display the results in Ascending or Descending order.