Open Resource Chart
Use this option to see each activity assigned to each resource. It produces a chart to show resource under and overallocations.
Instructions
On the Resources tab, in the Resources group, click Open Resource Chart to display a chart to showing resource allocations.
Generating the Resource Chart
-
Click the Open Resource Chart icon.
-
A new tab is created labelled Resource Chart.
-
Position the information window to the location that shows the dates you want to see displayed in the chart by dragging it to the left or right.
-
Select the resources you want to view from the Resources pane on the left side. To select more than one hold down the Ctrl key and select multiple resources. A list will appear below the Resources pane. The list of available resources is set up by clicking the Settings icon.