Animation
Use the Animation panel to display an animation of selected activities in Vulcan.
Tutorial
On the View tab, in the Vulcan group, click Animation to display the Animation panel.
Step increment
Select the increment of time for the animation. You can select Hour, Day, Week, Month, or Year.
Rate
Enter the number of steps per frame for the animation.
Show completed / Show remaining
Select whether to animate activities that have been completed or activities that are still remaining.
Display Precedences
Use this option to hide or show the precedence arrow in Vulcan.
Date
The scheduling Start Date is displayed on the Animation control and in the upper left corner of the Vulcan screen. The date will advance as the animation advances.
Icons
Previous
Click the Previous icon
to jump back to the previous step of the animation.
Stop
Click the Stop icon
to stop the animation.
Play
Click the Play icon
to play the animation.
Pause
Click the Pause icon
to pause the animation.
Next
Click the Next icon
to jump to the next step of the animation.
Last
Click the Last icon
to jump to the last step of the animation.
Loop
Click the Loop icon
to continue playing the animation on a loop. When the animation reaches its end, it will return to the beginning and play again.