Resource Productivity

Source file: epoch-setups-activities-duration-scripts.htm

The Resource Productivity subtab provides an interface for you to define the time it takes to perform a given activity on a solid. Generally, the duration is defined in terms of throughput and productivity rate as shown below.

Duration = Throughput/ Maximum Productivity rate

The Duration Scripts subtab provides scripting fields for both parcel -based or solid-based durations.

For those not comfortable with scripting, Evolution also provides an alternative interface which is activated by disabling scripts in the top right hand corner.

To check results, run the client evaluator and open the Live dashboard to create two pivot reports — one with the Material table as a source, and the other using the Activity table as a source. The pivot report with the Material table as a source is used to get the tonnages mined per parcel per solid. The pivot report with the Activity table as a source is used to get the total duration for an activity per solid. The result should be equal to or lower than the productivity defined in the software.