Stage Availability

Source file: origin-reserve-setups-constraints-stage-availability.htm

Use the Stage Availability constraint to flag the availability of pit stages for mining in each period.

The stages that are available for mining in a given period are marked in green, whereas those that cannot be mined in a given period are marked in red. To change the stage mining availability, double-click on the corresponding cell and select the required status.

You can apply settings manually for each stage in each period, or by copying the entered setting to the next period using the button. To copy the setting to all subsequent periods double-click the button. Alternatively, select a cell with the setting you want and press ctrl + c. Next, while holding ctrl on the keyboard, select all cells where you want to apply this setting and paste it with ctrl + v.