2. Configure the Setup
Source file: 2-strategy-setup-configure.htm
Once you create a Strategy setup, you need to configure it to include the necessary information for schedule generation.
Strategy setup configuration is divided into a number of tabs. Each tab represents an aspect of the setup the software requires to schedule the mine. The following is a list of tabs that need to be configured for a Strategy setup to be ready for server submission:
- Process Setup: Add process flow components to your setup.
- Tonnage & Grade: Specify total tonnage, ore tonnage, as well as primary and secondary elements.
- Lithology : Define lithology types that can be refined by each process in your setup.
- Targets & Economics: Specify the economic profile of your setup.
- Fixed Cut-Offs: Specify the process cut-off grade manually or allow the software to perform cut-off grade optimisation.
- Constraints: Specify a set of setup constraints in each period.
- Reporting: Add reporting items to the schedule report.
- Engine Parameters: Specify constraints surrounding schedule generation.
Note: Specifying engine parameters is optional.