There are two main types of Origin Solids setups: Material Movement and Equipment.

Material Movement setups do not contain trucks, road networks, or waste utility models. They do not consider the time taken to transport material from the pit to other locations (e.g. stockpile/mill/waste utility) when generating schedules.

Equipment setups contain trucks, road networks and waste utilities. They do consider the time taken to transport material from the pit to other locations (e.g. stockpile/mill/waste utility) when generating schedules.

Select which type of setup you want to create when first initialising a setup (see Initialisation of an Origin Solids Setup).

There are also a number of optional objectives that can be set: Min/Max, Blend and Net Present Value.