Process Blend

Use the Process Blend constraint to optimise the blend as a part of the value maximisation process. Process Blend is a soft constraint, so violating it will not cause a schedule to be invalid. When evaluating a schedule, Evolution checks how far the blend values are outside the specified range and then selects a schedule focusing on the blend result, rather than giving the priority to the net present value (NPV). You can select either a non-ratio or ratio blend, as well as the type of weighting applied to the blend.

Note:  The Process Blend constraint is a soft constraint, which means that Evolution will try to meet it when generating a schedule, but doing so is not forced.

Follow these steps to create a blend constraint:

  1. Using the drop-down menu, select the process that requires a blend.

  2. Configure the constraint. The possible configuration settings are as follows:

    • Control the blend of a single grade item.

      Note:  This is weighted by the Ore Capacity (tonnes) attribute set in the Tonnage & Grade.

    • Control the blend ratio between two grade items.

      Note:  This ratio can be weighted by any numeric block attribute from models in the setup.

    • Control the blend of a single grade item with a unique weight attribute.

      As you cannot select a unique Weight when the Is Ratio? checkbox is deselected, the following steps allow you to create a blend for a single grade item with your choice of weight attribute.

  3. In the calendar, under Blend, enter the Upper and Lower blend constraints. If Is Ratio? is selected, this value is a ratio.

  • Click the button once to copy the properties of the current period to the next period.

  • Double-click the button to copy the properties of the current period to the subsequent periods until the end of the schedule.

  • Alternatively, copy a cell's setting by pressing Ctrl+C , then paste it into selected cells with Ctrl+V.