Groups

Use Groups to add, modify, and remove attribute groups.


Instructions

On the View tab, in the Group group, click Groups to display the Group Setup pane.

Add a new item (Insert)
Copy (Ctrl+C)
Remove (Delete)
Set Current
Reset Current

General

Name

Enter a name for the group.

Description

Enter a brief description of the group.

Details

Attribute

Select an attribute from the list.  For more information about managing and modifying attributes, see Attributes.

From

Enter a value for the beginning of the group selection.

Length

Enter the length of the group.

Sort Order

Select whether to display the results in Ascending or Descending order.