Resource Levelling Setup
Use the Resource Levelling Setup panel to set step, date range, priorities, and other options for resource levelling.
Note: You can use Lava scripts to run automated tests for many of the most common options when setting up your project.
Instructions
On the Resources tab, in the Resource Leveling group, click Leveling Setup to display the Resource Leveling Setup panel.
Alternatively, you can press Alt+L to display the panel.
Leveling Range
Entire Project
Select this option to apply resource levelling to the entire project.
Date Range
Select this option to apply resource levelling only to a specified date range. If you select this option, select the start and finish dates in the Start and Finish boxes.
Activity Prioritization
Type
Select the attribute type by which to prioritize activities from the list.
Ascending or Descending
Select Ascending or Descending to indicate whether the attributes should be sorted in ascending or descending order.
Add
Click Add to add the selected attribute to the list.
Up
Click the Up
icon to move a selected entry up one row in the list.
Down
Click the Down
icon to move a selected entry down one row in the list.
Attribute
Indicates the attribute name for the entry.
Mode
Indicates whether the selected attribute is sorted in ascending or descending order.
Remove
Click Remove to remove the entry from the list.
Clear last levelling values
Select this checkbox if you want to clear previous levelling values.
Allow levelling to split activities
Select this option to split activities on a time allotted basis.