Sorting

Options for sorting data in ascending or descending order.


On the View tab, in the Sorting group, the following options are found.

Sorting

Add a new item (Insert)
Copy (Ctrl+C)
Remove (Delete)
Set Current
Reset Current

Instructions

  1. Start by adding a new item and naming it.

  2. In the Details section, under Attributes, select the attribute that you want to sort by.

  3. Select the Sort Order as either ascending or descending.

Current Sort

Select and display the current sorting.

Ascending

Select a column in the Gantt Chart area and then click Ascending to sort activities in ascending order by that column's values.

Descending

Select a column in the Gantt Chart area and then click Descending to sort activities in descending order by that column's values.