Sorting
Options for sorting data in ascending or descending order.
On the View tab, in the Sorting group, the following options are found.
Sorting
|
|
Add a new item. (Insert) |
|
|
Copy (CTRL + C) |
|
|
Remove (Del) |
|
|
Set Current |
|
|
Reset Current |
Instructions
-
Start by adding a new item and naming it.
-
In the Details section, under Attributes, select the attribute that you want to sort by.
-
Select the Sort Order as either ascending or descending.
Current Sort
Select and display the current sorting.
Ascending
Select a column in the Gantt Chart area and then click Ascending to sort activities in ascending order by that column's values.
Descending
Select a column in the Gantt Chart area and then click Descending to sort activities in descending order by that column's values.