Use the Allocate Precedence Group panel to create a new precedence group.
Instructions
On the Precedences tab, in the Precedence Group group, click New Group to display the Allocate Precedence Group panel.
New Group
Enter a group name in the field and click OK. The new group will be displayed in the Current Group list and in the Group Manager.