Allocate Resources
Use the Allocate Resources panel to allocate resources to selected activities.
Note: Â You can use Lava scripts to run automated tests for many of the most common options when setting up your project.
Tutorial
Resource Allocation and Leveling.
Instructions
On the Resources tab, in the Resources group, click Allocate resources to display the Allocate Resources panel.
Alternatively, you can press Alt+F10 to display the panel.
Resources
Allocating a Resource
Click Add
to allocate the selected resource to the activity.
Removing a Resource
Click Remove
to remove the selected resource from the activity.
Activities
Activity
Displays the name of the activity.
Allocated Resources
Displays the resources that have been allocated to the activity.
Rate Source
Displays the rate source of the activity.
Rate
Displays the rate of the activity.
Rate Source
Select Activity Manual, Resource Default, or Resource Manual, Partial Series, or Partial Parallel as the rate source.
User defined rate
If you select Resource Manual in the Rate Source list, enter a rate for the activity.
Activity %
If you select Partial Series or Partial Parallel in the Rate Source list, enter the activity percentage.
Apply rate
Click Apply rate to save your changes and apply the updated rate source, user-defined rate, and activity percentage to the activities.